Construction and project costs
On the Bill as a whole
For (2)
Matt Palmer argues that moving from annual cost budgets to a cost envelope gives flexibility to build efficiently, which this model enables.
Justin Madders argues that National Highways' evidence shows no overall cost increase from the fuel requirement, that it was set in the 2022 development consent order, and that the Bill is scheme-agnostic so such restrictions do not belong in it.
Against (11)
The Lower Thames Crossing's cost has risen sharply and the Government has not identified who will fund most of it, so the financing model and likely tolls are uncertain.
Restrictions on diesel and related fuels on construction sites will raise the project's costs, which will ultimately be passed on to people who cross the Thames.
Sam Dumitriu warns that the model could be used to take costs off the public books without adequate scrutiny, against a background of a high UK construction cost premium.
Alison Griffiths suggests the Bill should include stipulations to ensure the road is not overspecified and that costly elements such as sustainable diesel are not required.
Greg Smith argues that banning diesel in construction plant will make the project more expensive, and that regulators need freedom to apply common-sense cost control.
Olly Glover notes that some private finance initiatives have produced higher whole-life costs that burden taxpayers in other ways, implying caution about private finance.
Alison Griffiths argues that using HVO in construction carries substantial additional costs compared with white diesel, and asks for precise figures.
Greg Smith argues that HVO adds roughly 20p to 25p per litre over white diesel, raising construction costs that will ultimately feed into tolls, and asks the Minister to reconsider the requirement.
The toll level is likely to start at around the current Dartford level or higher, and future RAB valuations depend on initial construction costs. Pressure on costs is therefore needed to keep tolls down, though this is hard to write into the Bill.
The Bill is open-ended in its wording. The term 'economy' in clause 1 should expressly include freight and supply chains, and construction costs should be kept as low as possible within safety standards to reduce tolls.
Greg Smith argues that the breadth of clause 85 assistance needs clear limits and assurances on maximum exposure, and that the levy in clause 86 may not cover real costs, citing HS2 overruns.
On specific amendments
47 Conservative
For (0)
None.
Against (3)
National Highways' evidence was that HVO and electric plant costs are comparable to diesel and form a marginal part of total costs. Sustainable measures such as the 'greenest road ever built' matter to constituents.
Procurement specifies outcomes rather than fuel types, so the issue is for contractors. Fuel is under 1% of the Bill cost and is not a priority concern.
The sustainable measures on the project may carry a significant cost that has not been identified, which raises concern about the sustainability requirements.
reasoned amendment (unmatched to a specific amendment record)
For (1)
The Government's record of cancelling road schemes means there is no confidence it can deliver the Lower Thames Crossing on time and on budget, so the Bill should not receive a second reading.
Against (1)
The Conservatives are not credible in criticising cost control and delivery, given the cost escalation and cancellations on HS2 under their government.
39 Liberal Democrat
For (0)
None.
Against (1)
Traffic is already on the local network and the Bill aims to remove it, so there is no new burden to compensate; a broad compensation package would add costs and unintended consequences, and the Government does not intend to do a deal at any cost.
NC6 Liberal Democrat
For (1)
Infrastructure projects often overrun, so the incentive to minimise disruption does not reliably prevent serious harm to businesses and charities; the Minister should work on the clause at the next stage.
Against (0)
None.