Procurement and delivery bodies
On the Bill as a whole
For (4)
Will Godfrey argues that the Bill is enabling and that licences will be competitively tendered, giving a different scrutiny arrangement from the Railways Bill.
Matt Palmer responds that about two-thirds of UK contractors bid with HVO as standard, and that the market-tendered bid for this project was based on HVO, with the cost comparable to diesel.
Andrew Truscott argues that separating equity and financing from contracting, rather than bundling them, could give more certainty of deliverability.
National Highways would become the operator of last resort, which is sensible given it already operates adjoining parts of the network, and the RAB model is designed to provide long-term certainty.
Against (1)
Tolling licences are effectively open-ended, and there should be competitive re-tendering of operation at intervals rather than automatic continuation with the original builder.
On specific amendments
NC4 Conservative
For (2)
National Highways does not test the market across different fuel and power options and simply accepts what industry proposes, so the clause would require licence holders to prove value for money before restricting fuel choices.
Oral evidence suggested the lower Thames Crossing had not considered other fuels, so the Minister's account of the evidence is not fully accurate.
Against (2)
The development consent order did not specify any fuel type; most contractors proposed HVO voluntarily, and National Highways did not prescribe technologies, which the clause would effectively do.
It is not appropriate for the Bill to set out detailed provisions on how future licence holders procure fuel for construction and maintenance.
47 Conservative
For (0)
None.
Against (1)
Procurement specifies outcomes rather than fuel types, so the issue is for contractors. Fuel is under 1% of the Bill cost and is not a priority concern.