That's Debatable

9

Stage: Committee stage · Decision: NegativedOnDivision · Clause 51 · Liberal Democrat

What it would do

This amendment requires quarterly public disclosure of all buildings that have been signed off under risk-balancing guidance (such as PAS 9980) as "tolerable" without physical removal of unsafe materials.

Show the amendment's own text

Clause 51, page 28, line 31, at end insert—

“(3) Regulations under subsection (2) must require that—

(a) the register includes information on any building for which an external wall assessment has concluded that fire safety risks are tolerable without physical remediation or cladding removal having been completed; and

(b) information under paragraph (a) shall be published in a publicly accessible electronic format at intervals of no more than 3 months.”

Sponsors

Gideon Amos Liberal Democrat, Sarah Gibson Liberal Democrat

How members argued on this amendment, by party
No party data
4 for · 1 against (n=5)

Arguments made about this amendment

For (4)

for9 Gideon Amos

Buildings where remaining flammable cladding has been judged a tolerable risk should be publicly listed, because not all buildings have remediation plans and residents otherwise cannot know that the risk was accepted.

for9 Gareth Bacon (Orpington) (Con)

The amendment could act as a safety net, since tolerable-risk buildings may still have flammable cladding, and the Government should commit to considering this in drafting secondary legislation.

for9 Gideon Amos

The amendment asks only for a simple public listing of tolerable-risk buildings, so there is no clear reason to reject it.

for9 Gideon Amos

The Bill departs from an objective standard and lets owners conclude risks are tolerable, so listing such buildings publicly is a necessary and minimal step.

Against (1)

against9 Florence Eshalomi

Detailed requirements on registration content and quarterly publication are operational matters better left to secondary legislation, so they should not be placed on the face of the Bill.