Licence approval process
On the Bill as a whole
For (4)
Will Godfrey argues that the Bill is enabling and that licences will be competitively tendered, giving a different scrutiny arrangement from the Railways Bill.
During the initial period the ORR cannot grant a licence without Secretary of State consent, and decisions must be published. Clause 4 requires consultation with at least 28 days for representations before any licence is granted.
Clause 4 sets out a clear, transparent and accessible consultation process before a licence is granted, giving affected parties a chance to make representations.
Clauses 5 and 6 create a clear licence application process and flexible licence durations, with ORR extensions requiring the licence holder's agreement and advance notice.
Against (0)
None.