Regulator capacity and resourcing
On the Bill as a whole
For (8)
Will Godfrey argues that the ORR builds on its rail and road experience, has lead time to put arrangements in place, and is in discussion with the Department on resourcing.
Will Godfrey argues that the gaps are incremental rather than starting from scratch, and that he is reasonably confident they can be resourced before the first licence and price control.
Justin Madders says he is confident the ORR will be ready, acknowledging some additional capability is needed but arguing that the Bill sets out a clear regime.
The ORR must be fully equipped to discharge its road responsibilities, and a recent report indicated it needed to build skills and capacity. The Minister should reassure users that it will be capable.
The ORR will be resourced to deliver its duties, because the RAB model depends on an effective regulator.
Substantial preparatory work is under way to ensure the ORR can deliver its functions, and the Bill gives it the power to levy licence holders to fund this.
A plan is in place, and it would be unreasonable to have full readiness before the legislation passes. Evidence gave confidence that the right skills will be in place.
Special administrators are court officers with statutory duties to pursue the highways objective, must be licensed insolvency practitioners, and are subject to clear rules on joint appointments.
Against (12)
Ben Hopkinson argues that the ORR has never regulated a road RAB, creating a risk of setting the return too high or too low, and that the regulator may be slow to adjust to macroeconomic change.
Ben Hopkinson argues that the RAB model suits standardised assets with clear unit costs rather than one-off projects, and doubts the ORR's capacity and commercial expertise to negotiate effectively.
Greg Smith questions whether the ORR has the skills base and experience of RAB-type models to take on the new licensing regime without teething problems.
Tristan Osborne cites an independent review identifying resource gaps for construction-phase price controls and project-specific work at the ORR.
Tristan Osborne questions whether the ORR is ready and whether the regulatory landscape is firm enough to attract investor interest next year, noting investors' need for regulatory certainty.
The ORR has more experience with railways than roads, with only a small number of road-background executives. It needs strengthening, and an independent body alongside it should consider tolls and feasibility.
The ORR needs both independence and capability to take on the task of setting tolls. Its expertise is currently rail-focused, so significant strengthening in road-related capability is needed.
The ORR is looking to bring in new skills in economic regulation, but road regulation differs from rail, so the ORR will need to be significantly beefed up.
Stronger regulation is needed to protect the public, and the Bill should be supported by clearer reassurances that the regulator will weigh freight and logistics when considering economy and licence conditions.
The Department for Transport appears to be downplaying the ORR's capability in the Railways Bill, which raises doubts about whether the framework here is deliverable.
The Minister appears to accept the ORR is not yet capable, and evidence suggested the ORR does not consider itself ready. The Government should set out its plan.
Alison Griffiths argues that the Bill should require stakeholder remuneration to be comparable with similar public bodies, for transparency.