NC34
What it would do
This new clause would require the Secretary of State to prepare a Funding Certainty Framework, with funding for each Control Period set two years before it is due to start, to enable Great British Railways to plan effectively.
Show the amendment's own text
To move the following Clause—
“Great British Railways: Certainty of Funding
(1) Within 12 months of the passing of this Act, the Secretary of State must publish a funding certainty framework for Great British Railways (“the Framework”).
(2) The purpose of the Framework is to establish and maintain terms for the funding of Great British Railways.
(3) The terms of the Framework must include provision that—
(a) The Secretary of State may not vary, reduce, or reopen the funding settlement for an active Control Period, unless either—
(i) a statutory provision made after this Act amends Great British Railway’s duties requiring funding revision, or
(ii) an emergency has been declared within the meaning of section 1 of the Civil Contingencies Act 2004;
(b) the Secretary of State must publish—
(i) the confirmed funding determination,
(ii) the assumptions underpinning it, and
(iii) any exceptional circumstances to justify any adjustments,
within an active Control Period;
(c) the Secretary of State must agree the funding for the next Control Period not less than two years before it is due to start;
(d) when determining the funding settlement for a Control Period, the Secretary of State must take into account—
(i) the Long-Term Rail Strategy,
(ii) Great British Railway’s duties, and
(iii) whole system planning considerations across infrastructure, passenger services and freight;
(e) The Secretary of State must work with Scottish Ministers to align as far as possible funding determinations so that Great British Railways receives a single, coherent, funding determination no less than two years before the relevant Control Period starts.
(4) The Secretary of State must lay before Parliament a report on—
(a) any funding determination for each Control Period;
(b) any exceptional revisions of the funding determination for a Control Period within that Control Period;
(c) whether the Office of Rail and Road, or any other relevant body, has met any relevant deadline to confirm funding for the next Control Period, and where it has failed to do so, the reasons for that failure.
(5) Nothing in this section amends or removes the ability of Office of Rail and Road to carry out Periodic Reviews for each Control Period.
(6) The Secretary of State must annually lay before Parliament a report on—
(a) the stability of Great British Railways’ funding;
(b) the effect of any instability on—
(i) the efficiency of,
(ii) delivery of services by, and
(iii) management of risks associated with projects run by, or associated with,
Great British Railways.
(7) For the purposes of this section, “Control Period” has the meaning given in any final decision taken by the Office of Rail and Road which concludes each periodic review of access charges as described in Schedule 4A of the Railways Act 1993.”
Sponsors
Jerome Mayhew Conservative
Arguments made about this amendment
For (2)
New clause 34 has some merit in strengthening protections for the five-year funding review process.
Presented as a probing amendment, requiring funding for the next control period to be agreed two years ahead and limiting mid-period changes would reduce the boom-and-bust cycle that industry says adds around 30% to infrastructure costs.
Against (1)
Committing funding two years ahead is misplaced because economic circumstances change and a settlement agreed so early could be redundant; the ORR will set deadlines and the Bill already ensures timely completion.