NC35
What it would do
This new clause would require Great British Railways to create a long-term pipeline of infrastructure works.
Show the amendment's own text
To move the following Clause—
“Report on long-term pipeline for works
(1) Within 12 months beginning on the day on which this Act is passed, Great British Railways must publish a report containing a long-term pipeline of infrastructure and rolling stock work affecting any line or service operated by Great British Railways (“the works pipeline”).
(2) Great British Railways must publish further such reports within twelve months of the publication of the last such report under subsection (1).
(3) The Secretary of State must lay a report under this section before Parliament.
(4) Each report laid under this section must provide a works pipeline for the period of the following 15 years.
(5) Each works pipeline must include details of—
(a) infrastructure renewals;
(b) enhancements, including capacity schemes;
(c) digital signalling and technology programmes;
(d) major station works;
(e) rolling stock procurement;
(f) upgrade and refurbishment programmes.
(6) The works pipeline must specify the expected—
(a) timing,
(b) scope, and
(c) sequencing,
of renewal programmes, enhancements, and major technology transitions.
(7) The works pipeline must align with—
(a) The Rail Strategy’s objectives, and
(b) the funding provided for infrastructure and rolling stocks works during each Control Period.
(8) Each report laid under this section must include an assessment of—
(a) how the works pipeline will reduce inefficiencies in delivery of works, specifically in relation to—
(i) irregularity of gaps in funding, and
(ii) unstable or unreliable management of projects and programmes.
(b) how the works pipeline—
(i) has supported, and will support UK supply chain capacity;
(ii) has impacted protection of specialist skills within the rail industry; and
(iii) will support employment and apprenticeships.
(9) Each report must contain an assessment, during the year prior to its publication, of—
(a) progress in delivering any projects or programmes included in the works pipeline,
(b) any changes to projects or programmes included in the works pipeline, and reasons for those changes,
(c) the impact of the works pipeline on—
(i) industry investment,
(ii) inflation of costs in the rail sector, and
(iii) delivery capacity in the rail sector.
(10) Before publishing a report under this section, Great British Railways must consult—
(a) participants in the rail sector supply chain,
(b) rail industry bodies,
(c) the Scottish Ministers,
(d) the Welsh Ministers, and
(e) the Office of Rail and Road.
(11) Great British Railways has a duty to ensure that its integrated business plan and long-term procurement strategies pay due regard to the works pipelines included in the most recent report published under this section.
(12) On the day on which a report is laid before Parliament under this Section, a Minister of the Crown must make a statement to each House about how the works pipeline—
(a) aligns with the long-term rail strategy, and
(b) supports whole-network delivery priorities.”
Sponsors
Jerome Mayhew Conservative
Arguments made about this amendment
For (2)
A long-term pipeline of railway works would provide certainty for the supply chain and align with the Government's stated commitment to economic growth.
A visible long-term pipeline would reduce the feast-and-famine cycle created by short control periods, retain specialist skills, support apprenticeships and encourage supplier investment.
Against (1)
Forecasting works in detail over 15 years is unreliable and could create instability; the five-year integrated business plan and funding already provide the right balance.