Remediation deadlines and timescales
Within Remediation delay and timelines
· Scoped to this sitting (Commons, 17 November 2026) —
see across the whole Bill →
2 for · 2 against
Total across everything below — "on the Bill as a whole" and every amendment group combined. See each
section's own figures for what "for"/"against" means there specifically.
On specific amendments
"For"/"against" here means for or against that amendment passing — not the bill.
An amendment can itself cut either way (e.g. one that deletes a clause), so check
what the amendment does before reading the stance as pro- or anti-bill.
21
— NegativedOnDivision
Conservative
This amendment would amend the deadline for carrying out risk assessments until 10 months after the Secretary of State published an assessment of assessor capacity which demonstrates evidence that enough suitably qualified assessors exist to allow the deadline to be met.
For (1)
for21
Gareth Bacon (Orpington) (Con)
Gareth Bacon argues that the shortage of trained assessors and engineers means the deadline cannot realistically be met, and that residents should not be given false hope; the deadline should depend on demonstrated capacity.
Against (1)
against21
Florence Eshalomi
The Minister argues that the assessment duty is not a new requirement because the fire safety order already requires assessments, that capacity is sufficient, and that making the deadline conditional on a capacity assessment would create uncertainty and delay remediation.
24
— NegativedOnDivision
Conservative
This amendment would confirm that it is a reasonable excuse for a person charged under this section if they can demonstrate that the reason they were unable to meet the deadline was their inability to engage a qualified assessor.
For (1)
for24
Gareth Bacon
Gareth Bacon argues that setting deadlines without ensuring the means to meet them, such as trained assessors, is unfair, and that a reasonable excuse for inability to engage an assessor is needed.
6
— NegativedOnDivision
Liberal Democrat
This amendment replaces the subjective "as soon as reasonably practicable" standard for remediation completion with a fixed deadline of 24 months from the assessment deadline, unless tenants agree otherwise.
Against (1)
against6
Florence Eshalomi
The Minister argues that a fixed deadline would not speed remediation, and that a majority-tenant agreement mechanism would place an unreasonable burden on residents and could produce inconsistent outcomes between buildings.